1. Decoiler/Uncoiler

Disassemble the hot/cold rolled steel coil and send it to the leveler. There are two ways of unwinding: upper and lower unwinding. In the tube mill line field, we always choose the upper unwinding. 

Nomally, we have several types:

1.1, single side uncoiler, double side uncoiler

1.2, manual expansion, pneumatic expansion, hydraulic expansion

1.3, pneumatic brake/disc brake, hydraulic brake/disc brake

1.4, with coiler presser roller, the roller can be free roller, can be driven roller powered by dydraulic or by motor.


2. Shearing and butt welding machine

In order to ensure the continuous production of the production line, the irregular head and tail ends of the front and rear strips need to be cut neatly by a shear butt welding machine, clamped in the center, and welded together to form a continuous production strip.

Nomally, we have several types:

2.1, Full automatic shearing and butt welding machine

2.2, Half automatic clamp with shearing, but with manual welding


3. Material storage cage/accumulator

In order to meet the continuous production of welded pipes, a looper storage device must be installed to storage the steel strips to ensure continuous production of the unit.

There we have several types:

3.1, Vertical storage cage

3.2, Horizontal storage cage

3.3, Hozizontal accumulator

3.4, Vertical accumulator


4. Steel strip leveler (leveler)

Level the strip before forming. It is generally composed of an upper base, a lower base, a transmission device, etc. There are five rollers and seven rollers. In the welded pipe mill production line, there is usually a pinch roller in front of the leveler.


5. Forming machine

The tube mill forming machine will take a continuous strips to roll forming from breakdown roll stand/stations to fin-pass roll tooling stand/stations until the edges of the strip meet together to form a V welding angle.

The tube mill machine stands/stations are important.

The high precision machining job will be a good tube mill line quality guarantee.

The tube mill roller design is also important, which will influence the forming machine performance.

  


6. High frequency welding machine

Using the skin effect and proximity effect of high-frequency current, the metal of the weldment to be welded can be quickly heated to the molten state, and the welding is achieved by SQ roller extrusion. At this point the HF welding process melts and fuses the edges of the tube together and the material exits the weld station as the welded tube. The current frequency range of high frequency welding is usually 300-450KHZ, power is 100-1000KW. At present, the use of solid-state high-frequency welding machines is advocated. Now, we have the compact HF Welder, it will saving the energe and installation space.


7. Deburr, welding bead remove device

In the welded tube/pipe mill process, it is used to remove the weld burr in the welded seam position. 


8. Sizing machine / TH head straighter stations

The sizing unit usually consists of several driven horizontal stands/stations, passive vertical roller stands/stations and TH head straighter devices, which ultimately ensure the accuracy of the outer diameter and cross-sectional shape of the steel tubes, and also can improve the stress concentration and residual stress of the forming and welding production.

The tube mill sizing machine stands/stations are important.

The high precision machining job will be a good tube mill line quality guarantee.

The tube mill roll tooling design is also important, which will influence the forming machine performance.



9. Extra higher requirements for the welding seam treatment for some special applications

9.1, welding seam annealing (heat) treatment

In the ERW/HF welded pipe process, normalizing the weld including the heat affected zone, or performing quenching + tempering and normalizing + tempering treatment on the weld. The metallographic structure and mechanical properties of the weld are consistent with the metallographic structure and mechanical properties of the base material, so as to eliminate welding stress and improve weld performance. The most widely used is the intermediate frequency heat treatment machine.

9.2, Welding seam quality test, Ultrasonic testing

Non-destructive testing method for detecting internal defects of materials by using the principle that ultrasonic waves will diffract when encountering interfaces of different density media during propagation.

9.3, Welding seam quality test, Eddy current testing

Mostly used for on-line inspection of small diameter ERW welded pipe. Because the probe does not contact the surface of the pipe, high-speed flaw detection can be achieved. The detection of defects on the surface of the pipe is more sensitive, and the detection of defects on the layer and inner surface is not ideal. It can detect tube and weld defects, and can use impedance plane technology to analyze the location and depth of defects.


10. Tube Mill Roller / Roll Tooling

The roll is the main tooling mold for the production of high-frequency welded pipes, and is the main consumable part. The types of rolls are divided into casting rolls and forging rolls according to the manufacturing method. We nomally, adopt the fogged raw material to do rough machining, heat treatment to reach HRC 58~62, finish machining with ceramic inserts. They are divided into integral rolls and combined rolls according to the process method. Some combined roller, the middle part is made from Tungsten steel raw material, it is very hard and expensive, but ensure you a much longer using life to save your cost. The roller quality directly affects output and cost of the product. A good tube mill roll set should include below aspects: 

① According to the deformation modulus of the different raw material, perfect flower design to ensure the forming quality; 

② The roll material must have high precision, high hardness, high wear resistance and toughness, to ensure that it has a long life; 


If you want to learn more, please visit our website steel pipe manufacturing machine.

11. Cutting machine

Important equipment for the continuous production line of fixed-length cutting machines for pipes and profiles. Realize high-precision fixed-length cutting under the online running state of pipes and profiles. The cutting forms include sawing, rotary cutting and punching, and the driving system includes DC servo drive system and AC servo drive system, which are controlled by a microcomputer to cut to length.

Nomally, we have several types:  https://www.tubemill-line.com/Products/Tube-Mill-Cold-Cutting

11.1, Tube mill hot friction saw

11.2, Tube mill cold cutting saw


12. Automatic pipe stacking and packing into bundles

When the finished welded pipe with fixed length from cutting machien stations, we will make a run-out table to receive the pipes and packing them into bundles with labor jobs. Now, we have the machine for automatic steel pipe stacking and packing into bundles. Just operation the touch screen and type the requirements for what you need. It will save labor jobs and costs to make the round pipe into hex bundles, to make the square tubes into square bundles, and to make the rectangle pipes into rectangle bundles.

Nomally, we have several types:

12.1, The magnetic lift type for hex bundle, square, rectangle, and other

12.2, The forklift type for hex bundle, square, rectangle, and other

12.3, The simple-forklift type, with cheap cost, popular used, specially used for square, rectangle, and hex bundle.


13. Chamfering machine

The ends of the pipe cut by the hot/friction saw cutting machine generally have some cut defects and burrs. In order to meet the requirements of the subsequent process and the user's bevel, the burrs and the inner and outer edges of the pipe end need to be chamfering and trimmed. Flat-head chamfering machine is a device for milling both ends of welded pipe. It is composed of steel pipe feeding device, steel pipe clamping device, knife holder, transmission device, frame body and other parts. The working process of the flat head chamfering machine can realize automatic continuous and automatic control.


14. Hydrostatic testing machine

The hydrostatic test is the main equipment for the production of welded pipes. At present, the working process of the hydraulic testing machine used in the production of welded pipes is: feeding, clamping, water filling, pressurizing, holding pressure, releasing pressure, and discharging. The process also constitutes the basic action cycle of the test tube hydraulic press. Modern hydraulic test machines are controlled by PLC, so that each working process is automatically completed in sequence, and have the function of automatically recording test result parameters. According to the seal form, it can be divided into radial seal and end seal. Radial seal is a sealing ring matched with the inner diameter or outer diameter of the welded pipe. The expansion of the sealing ring under pressure to achieve the purpose of sealing the wall of the pipe. Its advantages are that the steel pipe is easily clamped and extracted, the seal is reliable, and the steel pipe is axially affected. The force is small and it is not easy to bend, but the structure of the sealing head is more complicated, there are more specifications, and there is a test blind area at the end of the pipe; the end face seal relies on the sealing material and the end face of the nozzle to press to achieve the purpose of sealing the nozzle, the advantage is that the test structure is simple , Good versatility, but higher requirements for sealing material performance and oil-water pressure difference ratio and servo control system.

Tips for maximizing tube, pipe mill efficiency (Part II)

Editor’s note: This is the second installment in a two-part series on optimizing tube or pipe mill operations. Read the first part here.

Finding, Reducing, Eliminating Bottlenecks

The pace at which the strip moves through the mill, from one station to the next—breakdown, forming, welding, sizing, and straightening—sets the pace for everything else. The mill’s reference speed is the maximum speed at which it makes a properly formed tube with a robust, durable weld.

The pace at which the strip moves through the mill, from one station to the next—breakdown, forming, welding, sizing, and straightening—sets the pace for everything else. The mill’s reference speed is the maximum speed at which it makes a properly formed tube with a robust, durable weld.

“The limitations often are in the entry and exit areas,” said Nelson Abbey, director of Abbey Products at Fives Bronx Inc. Efficient mill operations can be hampered by material handling and coil joining at the entry end; cutting the product to length and getting tubulars off the mill likewise tend to impose limits at the exit end.

Getting the Coil Into the Mill. If the coils are long, butt welding the outgoing coil to the incoming coil might take place every 15 or 20 min., and the operator gets a break between each one, Abbey said. If the coils are short and take only 5 min. or so to work their way through the mill, the end-joining process is likely to be the mill’s productivity limit. Longer coils mean less frequent mill stoppages and put less stress on the operator, he said.

Most such butt welds serve just one purpose—keeping the two coils joined until the new coil has worked its way through the mill—and the butt weld is discarded after that section goes through the cutoff.

For some applications, the butt weld serves a second purpose. For long lengths of coiled tubing, which can be miles long, the butt welds are a product feature and must be just as durable and leakproof as the longitudinal welds. Although an arc welding process is traditional, laser technology is making inroads relative this application, said Kevin Arnold, Midwest sales manager for IPG Photonics. The benefits are the same as those for making the longitudinal weld with laser technology, especially the minimal heat input and minimal ensuing distortion.

“The lower heat input and smaller heat-affected zone create a more durable weld,” said Mark Wagner, vice president of sales for Guild International. “A hard, brittle weld is prone to breaking as the joint moves through the mill. The tension can be enormous and often is more than enough to break the weld. When using a laser to join the coils, Guild has found that weld breaks are greatly reduced, and that the line can get back up to speed much quicker.”

“Another issue is the weld bead’s thickness,” he said. “Arc welding processes typically leave a thick weld bead. The additional thickness accelerates the wear on the roll tooling and other equipment, like inline tension levelers, so the weld has to be treated with either manual or automatic milling to reduce the weld bead, so the thickness is consistent. Laser welding doesn’t leave a raised weld bead, so it eliminates postweld treatments such as milling.”

The initial process, making the butt weld, also tends to go more quickly with laser welding than arc welding processes, he added.

Make It, Cut It, and Move It Out. When all is nearly said and done on the mill, the focus turns to the cutoff process. Some products simply take more time to cut than others. Even a product that usually is made at a fast rate and is easy to cut—say, a light-wall, small-diameter tube—can slow a mill down if the final cut lengths are short. The saw has to move at the same speed as the tube to make the cut, return to its starting position, then get back up to the mill’s speed to make the next cut. As the cut lengths decrease, the saw’s accelerations have to become increasingly faster to keep up.

Beyond the cutoff, carrying out finishing as part of the production process can create a bottleneck.

“Flushing the chips out of the tube, facing, and bundling them are additional processes that usually slow down a line,” Abbey said. The problem is that these run in different ways, Abbey explained.

“A mill runs most efficiently when it’s running consistently at a constant speed,” he said. “Finishing operations are start-and-stop processes.” On the surface, the difference is the pace of the mill versus the pace of the finishing steps, but it goes deeper.

“Every line stop creates at least one length of scrap,” Abbey said. Another drawback is the time it takes to ramp up the mill. “You don’t press a button and get back to full speed,” he said. “For typical mills, it can take 10 minutes or so.”

Depending on the system’s design, which often is influenced by limited floor space and obstructions such as building columns, such a connected system might just be inherently inefficient. Designing a generous buffering capacity between processes that run at substantially different rates is a good solution, depending on handling complexity. But if it’s impossible to include a buffer, or if the buffer is undersized, a lower overall production rate is inevitable.

It seems counterintuitive to connect a mill to finishing equipment, but indeed many mills are set up in this way. Depending on the product and how fast it runs through the mill, this setup isn’t detrimental to operational efficiency. For example, among mills designed to make products according to American Petroleum Institute specifications, about half of them can be connected to the finishing system with no effect on productivity, Abbey said. However, many such setups would run faster if they were disconnected.

What are the benefits? Such a setup uses less labor power than a disconnected system, and it takes up a smaller footprint than a disconnected setup, so many tube and pipe producers are willing to sacrifice some line speed and possibly lower overall product rates for these benefits.

On some mills, processes such as flushing and bundling are manual, which can be even more detrimental. In some cases, these end-of-mill processes bring the mill speed down by half, Abbey said. It’s a tradeoff—the company makes a smaller capital investment and brings in less revenue—but it can have unintended consequences. The operators become accustomed to the mill’s pace, and even if the company upgrades to automated flushout and bundling, it can have a lot of difficulty with the return on investment. After learning to do the job at 200 ft./min., the operators simply aren’t comfortable operating a mill that runs at twice that pace.

Changeovers

Selecting the right tooling for the job seems like an obvious first step, but mixups do happen. Mounting the wrong tooling—say, substituting tooling with a modified edge break for tooling with a standard edge break—makes it more difficult to make good product, and it compromises the tooling life, said Warren Wheatman, vice president of T&H Lemont’s Tooling Business Unit. The same goes for mounting the tooling correctly. When tools are reconditioned, the company that did the grinding usually provides a set of bearing block shims for proper mounting. In many cases, the shims get misplaced or their purpose isn’t understood and they are discarded. The tooling can’t do its job properly without the shims.

Selecting the right tooling for the job seems like an obvious first step, but mixups do happen. Mounting the wrong tooling—say, substituting tooling with a modified edge break for tooling with a standard edge break—makes it more difficult to make good product, and it compromises the tooling life, said Warren Wheatman, vice president of T&H Lemont’s Tooling Business Unit. The same goes for mounting the tooling correctly. When tools are reconditioned, the company that did the grinding usually provides a set of bearing block shims for proper mounting. In many cases, the shims get misplaced or their purpose isn’t understood and they are discarded. The tooling can’t do its job properly without the shims.

Getting the tooling aligned is the next step. Automated tool positioning devices are available, but many tube and pipe producers still rely on manual setups.

“Motorized adjustments with position feedback at each pass can help the setup go much faster, leaving only a small amount of manual tweaking to finalize the setup,” Abbey said. The same goes for the settings of the straightener, he said. The only caveat is that the maintenance staff has to be knowledgeable on how every device works and how everything is wired, and the company has to keep sufficient spares of every critical device in its inventory. Otherwise, just one bad component like an encoder can slow the process substantially, especially if used in an automated quick-change mill.

Does a tube producer need quick-change hardware, electronic positioning devices, and other hardware to reduce its changeover time? No. According to Abbey, good procedures and a motivated crew can cut changeover time nearly in half. He cited one 10-in. mill that had standard equipment and no quick-change features or setup assistance of any sort. While most such mills need five to eight hours for a changeover, one company with a motivated crew equipped with well-documented procedures could get it done in three and a half hours.

If a mill can accommodate rafts—subplates with tooling mountings—it can cut the mill’s downtime by a large amount, frequently up to 75%. It still takes time to do the changeover, so the company still needs the labor to change out the tooling on the raft, but it does so while the mill is still running and making money.

Of course, planning goes into this like it does everything else. Michael Strand, president of T&H Lemont, suggests three rafts per mill. While one raft is on the mill and making money, a second raft can be prepped with tooling for the next run. The rafts themselves have a large number of moving parts, so the third raft can be set aside for a teardown, inspection, and repairs if necessary.

“Threading is also a candidate for improvement on some mills,” Abbey said. “When threading a new strip through the mill, it’s common practice to jog the mill, starting and stopping numerous times. Once threaded, the mill is then typically run for a short distance to check the weld and do sizing adjustments, which generates a substantial amount of scrap. Simple improvements in this area can be obtained by streamlining the steps and by including interlocks with the welder so it can weld and jog at the same time.”

“It would generate less scrap if the company that made the welding power supply would change the controls so the mill could jog the material forward, weld, and scarf simultaneously,” he continued. “On large mills this is a necessity, and it really reduces the amount of scrap generated at each startup.”

Bringing It All Together

The essence of tube or pipe mill efficiency hasn’t changed, but in times like these, it’s more critical than ever. The revenue a mill generates while it’s running is always offset by the losses it incurs when it’s not, but times such as these seem to amplify the losses. Steel prices are higher than normal, and some materials simply aren’t available, so keeping the mill running and minimizing scrap are two considerations that are in sharp focus right now.

The essence of tube or pipe mill efficiency hasn’t changed, but in times like these, it’s more critical than ever. The revenue a mill generates while it’s running is always offset by the losses it incurs when it’s not, but times such as these seem to amplify the losses. Steel prices are higher than normal, and some materials simply aren’t available, so keeping the mill running and minimizing scrap are two considerations that are in sharp focus right now.

Best Practices. These industry experts, each of whom has decades of experience in the field, provided informed insights and perspectives regarding best practices:

  • “Every changeover involves downtime and scrap, and traditionally these are the two areas where tube and pipe producers can make the biggest gains,” Abbey said. “Every mill supervisor needs to study their changeover procedures.”
  • “It’s important to perform every maintenance action according to the schedule and document everything,” Strand said. Track every action on the mill, including the number of feet of product made by each set of roll tooling during each run, to stay on top of mill maintenance from a big-picture, years-long perspective.

  • “It’s helpful to use a status board or checklists that show each major step described clearly and concisely,” Abbey said. “Whether it is a changeover or a routine maintenance procedure, such as inspecting tooling, using checklists adds to consistency and efficiency,” Abbey said.
  • Using automated systems and devices to assist with mill setup can keep changeover time to a bare minimum. Abbey cited one special, automated mill that had its changeovers down to a science, relying extensively on such hardware, and it achieved consistent 15-min. changeovers. In that case, it was necessary to keep operator intervention to a minimum.

  • “Tube and pipe producers need to be careful how they use the mill,” said Stan Green, general manager for SST Forming Roll Inc. “Many of the materials available these days are much harder than common carbon steels, and the steel producers seem to introduce stronger materials all the time,” he said. Using a mill designed for carbon steel with a 50,000-PSI minimum yield strength to process 80,000-PSI material is going to accelerate the wear on every component on the mill and likely will break something—and sooner rather than later.

  • Inspections, maintenance, alignments, and yield work together, especially with tooling and roll stands.

    “The weakest point is the point that moves [out of position],” Green said. He cited a tiny bit of movement, anything more than 0.010 in., as too much movement. “Proper tooling position is important for a consistent process and to maximize yield, but you can’t keep the tooling in the right position if the bearings and shafts are worn,” he said.

Budgetary Matters. Regular maintenance is always important. It’s a critical issue day after day, week after week, month after month, year after year. Following the suggested maintenance schedule for every item isn’t more important when runs are shorter and changeovers are more frequent, but these activities are more likely to be delayed or even overlooked during difficult times.

“When times are good, tube and pipe producers hesitate to stop production for maintenance,” said Michael Strand, president of T&H Lemont. “When times are tough, they don’t want to spend the money.” And although many mills are running full-tilt right now, a sign of good times, some of the business conditions are tough—especially the sky-high cost of raw materials and the less-than-reliable supply chains, fallout from the pandemic.

“More money spent on the raw material and more time spent on changeovers means less money and time for scheduled maintenance,” said Dan Ventura, president of Ventura & Associates. It’s not just a matter of spending money, but spending it wisely. It takes high-quality machinery and consumables to make high-quality products, and better investments can pay off.

“When buying tooling, many tube producers work right off the quotes and make decisions based on price,” Strand said. If it’s not a trustworthy tooling provider, it’s impossible to know if the tooling is made to the right design for your mill, made from the proper alloy, and if it was heat-treated properly.

The same goes for the ferrite used in the impeder, said John Holderman, general manager for EHE Consumables.

Few would go so far as to research something that many would regard as a minute detail, but ferrite varies in grade, which equates to its capacity to do its job. To provide the best use of electrical energy, the ferrite must have three characteristics: low losses, high permeability, and high saturation of flux density. For durability, it needs construction methods and binders that resist heat.

The same goes for everything else on the mill. Frugality is one thing, but taking that too far can mean dedicating disproportionate time and effort on repairs and incurring more downtime than necessary as the equipment ages.

Breaking the Speed Limit. If a company does adhere to every best practice, where can it go from there? For those who are prepared, there is one more boundary to be pushed.

“When everything is dialed in, the operator has one more thing he can do to maximize throughput,” Abbey said. “A motivated operator can run the mill a little faster than he’s accustomed to.” Abbey acknowledges that this means the operator has to work outside of his comfort zone, and this isn’t easy, but this is one last area for productivity gains, and perhaps the only way to find out what the mill really can do.

Contact us to discuss your requirements of Tube Embossing Machine. Our experienced sales team can help you identify the options that best suit your needs.